Update on Sanctuary Remodel 7/12/2010
Here is a brief status for renovation as of the end of today. Today was day 8 and our goal is to be done by July 31 which would be on day 27, so we are right around 33% of our elapsed time.
I feel like everything is moving along really well. The great start due to the excellent volunteer kickoff day made a huge difference. Virtually all demolition tasks are complete, with just a few spots of stuck carpet pad and a cable or two still to be removed. AJ removed the lights, hangers, and chandeliers, and also the old speakers. Beams one and two are now clear and ready for the new stuff to go up. Holes where the old lights were attached have been covered with painted trim covers.
Jon has a pretty good start on the electrical. He has completed installation of all the lower conduits including the A/V conduits around the main and lower platforms. The conduits from the panel to the dimmer system are in place, and also a spare conduit for electrical that Jon threw in for us. Conduits are also running into the closet area for AV and electrical there. All of the floor access boxes are ready to be framed in. No electrical cables or A/V cables have been pulled yet, but I expect that to happen over the next couple days.
Our first major issue was the lack of space to get conduits through the HVAC chase, but it has turned out to be a positive because going through the floor channel is going to save us more than it costs, in part due to some very reasonable pricing by Chuck on the floor trench. It has allowed us to use the cheaper PVC conduits for the long runs to the panel, which in turn made it feasible for AJ and I to install the two large AV conduits in that run.
Roger has the framing moving along with several of the platform segments already built and ready to be installed. He has had some good help from Larry and Walt. Denny and Walt have purchased materials for the tech center platform and have assembled a large portion of the base deck.
Chuck was able to get all of the concrete poured and finished today, including the ramp, the floor trenches, and the steps around the altar. All of that looks really nice.
Rick Short was on site today and he is thinking installing the carpet with a pad and tack strips is probably going to be better than gluing the carpet with no pad. That will solve any issues with glue not sticking to "damp" concrete, and will also do a better job hiding some of the imperfections that are part of a remodel situation. He will absorb any increase in cost due to the pad vs the glue.
I would anticipate that alot of the framing and decking will get done this week. Also most of the electrical and AV cables on the platforms will get pulled this week. AJ is bringing in a speaker system to demo this Wednesday evening around 6PM so all who are available should try and be there to listen - will be using the lift to allow us to hear the speakers from their approximate location above.
We ran into some minor issues making the platform front, angles, and steps work just right so we ended up solving this by expanding the "straight" platform dimension a bit, and at the same time reducing the length of the angled areas. I think this worked out to be a better solution as it keeps the aestetics of the angles but also maximizes the more usable straight space.
Barb Woods and Judy Willits painted a few sample areas with two different paint colors, biscuit is almost identical to the current color, and the test spots of the color bagel look really nice and I think would be a great improvement if that is what we end up doing (Trustees).
We may be able to get started on some of the beam work later this week for lighting, etc, but definitely by early next week. Jon and AJ both have quite a bit of work up there, including conduits and hanging of the black pipe for the lights.
I hope to have a report on the budget soon, but not quite there yet. I have a pretty positive feeling about it and hopefully can confirm that in the next couple days.
Thanks to all who have donated their time, talents, and funds to date - I think we have a very good chance of getting the total project done, and even done on time!
Mike
Trustee`s Meeting May 11th. 2010
Those present: Denny Woods, Mary Armstrong, Judy Willits, Larry Gray, Sheri Smith, Mike Poor, Becky O`Dell, John Thomas
The meeting opened at 7:03 p.m. with prayer led by Denny.
Financial Report:
Repair and Maintenance-$16,111.00 Improvement Fund-$19,586.00
Old Business
*Minutes were approved
-Light pole insurance money has been received so we are ready for installation
-Check on date for Painting of the Celebration sign and fencing.
- A landscaping/ work day has been approved, Steve Harding to head it up!
-Steve Harding reported to the trustees that he thought we had to many emergency lights
-Steve gave us a bid from his old company to fertilize and weed control for our church yard.($515.00)
We have given Steve permission to plant 14 trees as a gift from the Jamar Nursery. Moving of the trees total $1,500.00
Steve asked the committee again about a sound room for his equipment. We are hoping to see some plans drawn by a professional architect. Mike will check on this for us.
-Denny will look into railing under stair`s to hide compressor in CMC
-No ideas on Red Letter floor
-Larry Gray fixed our lighting problems (exit signs,ballasts)
-Mary will give Steve Harding the OK to to buy a new computer for $500.00
-Mike has meet with Koorson (Alarm co.) and has the alarm system working as it should
-Denny fixed the bathroom stalls doors and some lighting in the bathrooms
-J.T. wants to build a deck covering at the parsonage 14/12, the ok was given
J.T. will have the carpet cleaned their in the next two weeks.
-Bob will arrange a painting day this summer, We will hire the high work to be done, estimates to come
-We looked at the estimate for the air conditioning compressor, Sheri will check into it.
New Business
-lighting in the old part of the church and or new bulbs for the gym lights
-When will Upward and or the Scouts hang the large flag`s in the gym,
-Also the light outside that shines on the flag pole.
-Have the occupancy sensors in the CMC bathrooms been installed
-The charge conference approved the Sanctuary Renovation On Sunday, April 18th. 2010, Bert Kite residing, District Superintendent
-The UMM will pay $500 towards the large garbage disposal for Kit. C. Larry Gray will look into installing the small sink disposal
-The Pathfinders SS class bought 6 new 6 foot tables.
-Bill McCoy would like to sand/paint the old church bell in 2 weeks!
-Denny spoke about the Fuller project and the Help Build Hope/Mission wknd
-The OK was given for to have the parsonage`s lawn treated.
-Dave Yount is looking into an out door permanent basket ball goal
-sidewalk from town/gift of base cove from Short carpet/lawn cutting twice weekly
The meeting was adjourned with prayer by J.T.
Trustee`s Meeting May 11th. 2010
Those present: Denny Woods, Judy Willits, Larry Gray, Sheri Smith, Mike Poor
The meeting opened at 7:04 p.m. with prayer led by Denny.
Financial Report:
Repair and Maintenance-$15,568.00 Improvement Fund-$7,233.00
All Business
*Minutes were approved
--Check on date for painting of the Celebration sign .
--Fertilize and weed control for our church yard ($515.00) was done
--Landscaping day was not very well attended!
--Computer for Steve Harding?
--Larry Gray will look into railing under stair`s to hide compressor in CMC,
Mike Poor and he are working together to get the light pole installed.
--Denny will check on our contract with Koorson, and work on Insurance policy update
--Bob Mitchell got 4 bids, we decided on A J painting, a local contractor $2,450 for all work
--We looked at the estimate for the air conditioning compressor, decide in June
--Mike Poor to work on our lighting in bathrooms and work with the Scouts and recreation
when they install the new flags and lighting reported by Becky Odell
--Sheri will speak with Korey Collier to ask when new light sensors will be installed
--Sheri will call AMCO about the emergency phone in our elevator
and call Muegge to install large garbage disposal for Kit. C.
-- Larry Gray will look into installing the hand sink disposal
-- and a new mowing concept at his son`s church
The meeting was adjourned at 8:35